A literature research was conducted and identified ten studies reporting major delay factors for construction projects in Ghana. All these studies are based on self-administered questionnaire survey of views and perception of project participants. Over forty construction delay factors were reported in the literature, and have identified as one of the major construction delay factors by one out of the ten studies on Ghana. A thorough review of these ten studies was undertaken to identify major delay factors for construction projects in Ghana. With respect to the major construction delay factors identified, remedial measures to improve the schedule performance of construction projects in Ghana are presented.