Procedures and Issues within the Contractors Classification System in Saudi Arabia

Authors: Saud Almutairi, PhD, Dean T. Kashiwagi, PhD, Jacob S. Kashiwagi, PhD, Mohammed Alghatany, M.S., Kenneth Sullivan, PhD

PDF

 

Research has shown that construction projects in Saudi Arabia have exhibited poor performance for the past three decades. The Saudi construction environment lacks many of the best practices found in more developed countries, such as prequalification, bonding, and 3rd party insurance. The government’s construction relies on the low bid delivery method and prequalified contractors using the Contractors’ Classification System (CCS). However, the current CCS does not accurately represent contractors’ capabilities and performance. This paper reviews all of the parts of the Saudi CCS, including the workflow and the evaluation criteria. This paper proposes to analyze the current classification system and identify the issues incorporated in the CCS regulations and classification process. This paper summarizes the authors’ critical review through interviews that have been carried out with key persons in the CCS. Several issues with the CCS are identified, such as no performance feedback, complexity of the system, and high resource requirements. The findings identify that the current CCS must be modified to be able to accurately reflect contractor capability and performance.

Keywords: Contractors Classification, MOMRA, Contractors’ performance, Saudi Arabia.

Introduction

Saudi Arabia is one of the strongest economies in the Middle East where oil is considered one of the most important economic resources. Over the past 30 years, the Kingdom of Saudi Arabia (KSA) has seen a considerable growth of the construction industry and a major increase in large-scale projects. With investments growing in the construction sector in Saudi Arabia, between 2008 and 2014, to total approximately $574.7 billion [1]. However, several studies by construction researchers have shown that the construction industry in Saudi Arabia is suffering from poor performance (e.g. causing the delay of projects and significant financial losses). Time overruns is thought to be amongst the most continuous and difficult issues in development ventures (and their completion) in the KSA. According to Zain Al-Abedien, it was found that delays were the standard for 70% of the projects taken up by the Ministry of Housing and Public Works (1983) [2]. Six years later Al-Sultan reported the same rate (1989) [3]. He reported that 70% of Saudi Arabia’s public projects had time delay issues. Al-Khalil and Al-Ghafly found the normal schedule delay in the public projects in Saudi Arabia is 58% longer than originally proposed (1999) [4]. Al-Ghafly studied the contractual workers and the specialists and found that the temporary workers believed that 37% of the tasks experienced deviations (1995) [5]. In 2006, it was found in Eastern Province that 70% of projects experienced projects delays and the normal delay in projects is between 10% and 30% [6]. A study directed by Al Turkey that 80% of projects were liable to negatively impact budgets, while 97% experienced time issues [7].

Saudi government relies on the low-bid delivery method and the Contractors’ Classification System (CCS) as the basis for prequalifying contractors for most of the public agencies work to ensure contractors’ capabilities and performance [8]. According to the Ministry of Municipal and Rural Affairs (MOMRA) website (2016), the Contractors’ Classification System was originally established in 1973. The CCS was administrated by the Contractors Classification Committee. Following administration by the Contractors Classification Committee, the Ministry of Housing and Public Works took over the responsibility from 1979 to 2004. In 2004, the administration of the CCS was taken over by MOMRA. There are 4,113 classified contractors in 5 grades across 29 disciplines. In the past 3 years, 884 certificates have been issued per year (registration, renewal or upgrade in grade status).

The current classification system operates within 29 fields and 5 grades. The function of the classification grades is to determine if a contractor is classified in a certain field. Through grades 1-5, the contractor will be limited to a certain maximum financial value of a project and a contractor can carry out the project in his specific field. If a project does not exceed its upper limit, the contractor is not required to have a grade. An example of some of these fields and financial limits are given as follows in Table 1 [9].

Table 1: Example of fields and financial limits (in Millions of Saudi Riyals).

From the literature, researchers have studied the Saudi contactors’ classification system. Alsugair and AbuThnain in 2011 conducted a questionnaire to assess the Government Contractor Classification System in Saudi Arabia [10]. The main conclusion of this study was that the current classification system does not properly reflect the contractors’ capabilities. However, the study has not been able to determine the reasons of this issue. Mahamid in 2014 conducted a research study to identify the common direct and indirect (micro and macro level) dispute causes in residential building projects in Saudi Arabia [11]. This study refers that the Contractor Classification System in Saudi Arabia is one of the highly relevant causes to construction problems that lead to dispute between construction parties. In 2012, Riyadh Chamber of Commerce conducted a study of the difficulties facing the construction sector, the study found that the system and procedures of the contractors’ classification system is the most important and influential factor [12].

Problem

The Saudi construction industry has had poor performance for the last 3 decades because of contractors’ low performance. The contractors’ classification system (CCS) is the only system used in most of the public agencies in Saudi that prequalifies contractors to ensure their capability and performance. The contractors’ classification system is facing difficulties in accurately reflecting the contractors’ capabilities and performance. According to the literature, it shows there are a very few studies that discuss and evaluate the CCS. The reasons behind these difficulties have not yet been identified in previous research.

Proposal

Current literature suggests that CCS is inefficient. However, no credible research has conducted an in-depth investigation of the issues of the current classification of workflow, evaluation criteria, regulations and process. This paper proposes to research the CCS and identify the issues incorporated in the CCS regulations and classification process.

Methodology

The methodology in this research starts by reviewing and analyzing the current CCS process including the workflow and evaluation criteria. The authors will identify the main issues in the system by conducting interviews with MOMRA. The authors interviewed the strategic plan team in MOMRA and key persons in the CCS in several meetings starting from October 2015. In total, 10 officials were selected and interviewed based on their experience in the CCS system (average 15 years) and their positions in MOMRA and CCS agency (general, legal, technical, services directors, and consultants who work with the agency). Interviews were conducted face to face and the objective of the open-ended questions was to evaluate the current CCS process and identify the root causes of the incorporated issues.

In order to answer the main question of the study, “Why doesn’t the current CCS accurately evaluate and reflect contractor performance and capability?” face-to-face panel interviews were scheduled with the 10 chosen members of MOMRA. The following questions were asked:

  1. Could you describe the flow of the current CCS structure?
  2. What are the evaluation criteria of contractors’ capabilities?
  3. What are the main issues in the CCS system?
    1. What are the internal issues in the CCS system?
    2. What are the external issues to the CCS system?
  4. Does MOMRA have any strategic plan to improve the CCS system?

Results

In the interviews, the authors asked the interviewees to describe how the current CCS worked. The collected information shows that contractors bid on projects that have been assigned grades based on project budget, and the CCS plays the role of assigning contractors the maximum grade of projects they can bid on. MOMRA manages the CCS, and contractors are assigned a maximum grade through certifications that expire after 4 years. Interviewees explained that contractors could apply for any project-grade certification regardless their current certification status. MOMRA reviews the contractor’s application and determines whether the contractor can receive their requested certification through an evaluation process. Contractors apply by first filling out classification forms based on the requested certification grade. MOMRA then performs an evaluation based on legal, technical, and financial criteria. After MOMRA performs the evaluation, MOMRA informs the contractor if their application is accepted or denied. If accepted, the contractor is then certified to bid on projects for 4 years without additional evaluation until the certification expires. After the certification expires, the contractor must renew his classification. The contractor may choose to apply for a higher-grade certification, in which the application and evaluation process must be repeated. (See Figure 1)

Figure 1: Contractor Classification System Structure.

The main requirements in the legal analysis include items such as the address of contractor’s main office (Saudi contractor and non-Saudi), client endorsement, names of the owners of the company, partners or major shareholders (with their nationality), the proportion of capital into the company, the field of grade classification being sought and commercial register. In order to receive this information, MOMRA has created forms that all contractors must complete and submit to be eligible for classification. There are a total of 10 general forms to be filled out by the contractor, 4 forms filled out by MOMRA employees, and 1 form filled out by the contractor’s clients. If the contractor passes the legal analysis, then they will proceed to technical and financial.

The technical criterion contains 5 major elements including: the client’s survey of the contractor, equipment, a site visit, personnel involved, and project details. The personnel element includes managers, engineers, technicians, and specialists. The project element includes project value, monthly value, yearly load, high value project, and continuity. The total estimated weight in classification rating for the technical criteria is 70% (table 2).

The financial analysis contains three major elements including balance sheet, profit/loss, and financial ratios. The balance sheet includes total assets, net worth, and working capital. The profit/loss includes total revenue, net income, net cash and income. The financial ratios include liquidity, profitability, leverage and efficiency. The total estimated weight in classification rating for the financial criteria is 30% (table 3).

Table 2: Classification Rating of Technical Analyst.
Table 3: Classification Rating of Financial Analyst.

After the interviewees described the current CCS, the authors then requested feedback on potential issues within the system. Among the main criticisms of the CCS is that it does not accurately prequalify contractors. Interviewees expressed multiple frustrations and described contractor behavioral issues due to the CCS. The interviewees explained certification is only important to contractors every 4 years since there is no contractor regulation within the 4-year period.

The interviewees then described internal system issues, which were broken down into two categories: system philosophy and evaluation process.

System philosophy issues:

  • The traditional approach of the CCS System includes attempts to collect and utilize technical information from contractors to predict future contractor performance over the course of 4 years.
  • Once a contractor is classified, it can be assumed that they can perform projects in their classification grade and field for 4 years. However, this assumption may not be valid as the 4 years period is too long in which the contractor’s level of performance and capability may change due to many reasons such as projects overload or financial issues.
  • The CCS agency employs technical experts to make decisions on the technical information obtained from the contractors to predict future. These decisions are considered subjective and are not related to the actual contractors’ capability or performance.
  • The CCS only required contractors to turn in information once every 4 years; the contractors are not tracking and providing their performance (cost and time deviation or doing risk mitigation) to MOMRA which results in MOMRA not being able to analyze the actual performance of the contractors, the industry and the CCS.

Evaluation process issues:

  • Due to the large quantity of technical information required, there is an increase in the complexity of the system (e.g. increased subjective decision making, decreased transparency and increased need for more technical information to attempt to mitigate risk).
  • The complexity of the system creates confusion for both agencies and contractors involved in the CCS process. The confusion creates complaints and increased effort from CCS stakeholders.
  • Site visits are only an assessment of one project. The main office visit aims to verify the contractors financial, technical, and administrative information provided in the forms with records and documents calculations for the contractor and evaluation. This is also the verification of engineers and technicians employed by the contractor. The method of performing office visits is aimed to provide an audit of the applicant contractor; however, a large quantity of information is required to be checked in a single short visit. In addition, contractors sometimes delay the site visit, which has a negative effect on the process of the classification.
  • The visit is considered very costly to the CCS organization and proven to be non-sustainable. Site and office visits annually take 31.8 % of the MOMRA employees’ workload and 11.9% of the agency expenses. In addition, the visits may not be an effective control measure.
  • The financial analysis consists of 11 criteria and most of the financial criteria consist of repeated information and are too complex for the contactor to understand.

After explaining the issues within the current CCS, interviewees described issues external to the system that affected contractor performance. These issues are not currently included in the evaluation process. Saudi Arabia has no mature bonding program, no effective third party insurance system that covers workers compensation, no building, health, or safety insurance, and no regulatory Occupational Safety and Health Agency (OSHA) organization. The KSA has no mature prequalification system that uses financial organizations such as Dunn and Bradstreet (D&B) that gives a benchmark check of a contractor’s financial stability. The licensing bureau in Saudi Arabia is not a regulatory entity that can affect a contractor’s classification rating. In addition, there is no integrating system in Saudi Arabia to utilize the risk mitigation capability of timely and accurate classified contractor performance information. MOMRA has the responsibility to mitigate the construction risk through its contractor classification system (CCS).

The authors then asked the interviewees if MOMRA had any strategic objectives for improving the CCS. The interview results suggest that MOMRA’s strategic plan seeks to simplify and minimize the subjectivity of the CCS, motivate contractors to participate in the CCS, and improve performance. Additionally, MOMRA’s plan states that they want to develop, support, and improve the construction sector performance by creating a state of the art knowledge and information system.

Conclusion

This paper examines the results of interviews structured to examine the Saudi CCS, including the workflow and the evaluation criteria. Several issues incorporated in the CCS regulations and classification processes have been identified. The main issue in the CCS system philosophy is that there is no contractor regulation within the 4-year classification period. Contractors are not tracking and providing their performance to MOMRA resulting in MOMRA not being able to analyze the actual performance of the contractors. The 4-year period is considered too long as the contractors’ level of performance and capability may change drastically in 4 years due to several potential reasons such as, employees’ expertise, projects overload or financial issues.

The underlying issue of the evaluation process is that it requires a large amount of technical information from the contractors. This requirement increases the complexity of the evaluation, increases subjective decision-making, and decreases transparency by making it difficult for multiple parties to clearly understand. Many parties consider the evaluation process to be highly inefficient because it is too costly and time consuming. In addition, the financial analysis criteria are repetitive and too complex for the contactor to understand. Finally, the CCS does not adhere to proven standers procedures in contractor evaluations such as prequalification, bonding, and 3rd party insurance in the Saudi construction environment made the situation more difficult on CCS. It is recommended that the current CCS should be re-evaluated and revised to accurately reflect contractor capability and performance.

References

[1] Ventures Middle East (2011) The Saudi construction industry, Abu Dhabi.
[2] Al-Abedien, Z. (1983, May). HM, 1983 (About the Effect of Delay Penalty On the Construction of Projects and Modification Proposals, Proceedings). In First Saudi Engineering Conference, Jeddah, May (pp. 14-19).
[3] Al-Sultan, A. S. (1989). Determination of construction contract duration for public projects in Saudi Arabia (Master thesis, KFUPM, Dhahran, Saudi Arabia).
[4] Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Important causes of delay in public utility projects in Saudi Arabia. Construction Management & Economics, 17(5), 647-655.
[5] Al-Ghafly, M. A. (1995). Delay in the construction of public utility projects in Saudi Arabia (Doctoral dissertation, King Fahd University of Petroleum and Minerals).
[6] Assaf, S. A., & Al-Hejji, S. (2006) Causes of delay in large construction projects. International journal of project management, 24(4), 349-357.
[7] Al Turkey (2011) The reality of projects in terms of organization and structure, and the reasons for success and failure In Saudi Arabia. Alwatan Newspaper. (Online) accessed on 15 September 2016 available from http://www.alwatan.com.sa/Local/News_Detail.aspx?ArticleID=49126&CategoryID=5.
[8] Bubshait, A. A., & Al-Gobali, K. H. (1996). Contractor prequalification in Saudi Arabia. Journal of management in Engineering, 12(2), 50-54.
[9] MOMRA. (2017). Contractors classification agency. Retrieved October 12, 2016, from, https://contractors.momra.gov.sa.
[10] Alsugair A. and Abuthnain M., “Assessment of the government contractor classification system in Saudi Arabia”, Advanced Materials Research, V250-253, PP345-355, 2011.
[11] Mahamid, I. (2014). Micro and macro level of dispute causes in residential building projects: Studies of Saudi Arabia. Journal of King Saud University-Engineering Sciences.
[12] Riyadh Chamber of Commerce (2012). http://chamber.sa/mainpage/pages/homepage.aspx.